Projects Under Implementation



MAU

Project :
 

Multi Village Water Supply Scheme for 58 Villages of MAU, Dist. Chitrakoot, Uttar Pradesh

Client :
 

UPJN, Lucknow

Project Value (Rs Crs) :
 

94.43

Project Description :
 

Survey, Design and Construction, of Multi Village Potable Drinking water supply systems for 70 LPCD capacity

Guwahati (C3)

Project :
 

South Central Guwahati Water Supply Project (C3), Assam

Client :
 

GMDA, Guwahati

Project Value (Rs Crs) :
 

140.92

Project Description :
 

Design, supply, installation & commissioning of water supply project for the South Central Zone including 5 years O&M

Agra

Project :
 

Laying of Water Transmission Mains for Agra City

Client :
 

UPJN, UP

Project Value (Rs Crs) :
 

123.08

Project Description :
 

Supply and Construction of 12km Pipeline (800 mm dia) from Karab to MathuraWTP, 17.5km pipeline (1600mm dia) from Yamuna river to WW-I WTP and 1.5km pipeline (1600 mm dia) from Yamuna river to WW-II WTP

Nepal (Package 1)

Project :
 

Laying of Bulk Distribution System and Construction of Service Reservoirs (Package 1), Kathmandu

Client :
 

KUKL, Nepal

Project Value (Rs Crs) :
 

117

Project Description :
 

Design, Supply, Laying of 9 Km DI pipeline (700mm-1400 mm dia.) and Construction of 3 GLSR – 8000, 8500 & 9500 cum each

Rajauli

Project :
 

Rajauli Multi Village Piped Water Supply Scheme, Distt. Nawada, Bihar

Client :
 

PHED, Patna

Project Value (Rs Crs) :
 

102.29

Project Description :
 

Design and build of all system components of Rajauli Multi village piped water supply Scheme including 5 years O&M on DBOT mode

Tikamgarh

Project :
 

Niwadi Multi village Water Supply Scheme, Distt. Tikamgarh, M.P

Client :
 

MPJNM, Bhopal

Project Value (Rs Crs) :
 

84.54

Project Description :
 

Design, Supply & Laying of pipelines for bringing 16.31 MLD treated water (16 hours flow) from the Source Paricha Dam, located near Village - Bheetri, Block Niwadi, District – Tikamgarh, to 21 villages & 2 urban towns

Sehore

Project :
 

Baneta Multi Village Rural Water Supply Scheme, Distt. Sehore, M.P.

Client :
 

PHED, Sehore

Project Value (Rs Crs) :
 

82.66

Project Description :
 

Design, Supply & Laying of pipelines for bringing 11.40 million litre /day of treated water in 16 hours flow from the Source Narmada River, located near Village - Baneta, Tehsil –Budni, District –Sehore, to 74 villages and 2 urban town

Guwahati (C1)

Project :
 

North Guwahati Water Supply Project (C1), ASSAM

Client :
 

GMDA, Guwahati

Project Value (Rs Crs) :
 

74.75

Project Description :
 

Design, supply, installation & commissioning of intake facilities, transmission mains, 62 MLD WTP and reservoir including 5 years O&M

Sidhi

Project :
 

Majholi Multi Village Water Supply Scheme, Distt. Sidhi, M.P.

Client :
 

MPJNM, Bhopal

Project Value (Rs Crs) :
 

66.78

Project Description :
 

Design, Supply & Laying of pipelines for bringing 9.8 million litre of treated water in 16 hours from the Source Banas River, located near Village - Parasili, Block Majholi, District – Sidhi, to 31 villages

NTPC, Gadarwara

Project :
 

Make-up water piping package for Super Thermal Power Project at Gadarwara

Client :
 

NTPC, MP

Project Value (Rs Crs) :
 

66.69

Project Description :
 

Raw Water Transmission Pipeline (two parallel Cross Country Make-up Water Main Header / Rising Main) for 2 x 800 MW NTPC Power Plant

Morena

Project :
 

Narhela Multi village Water Supply Scheme, Distt. Morena, M.P.

Client :
 

MPJNM, Bhopal

Project Value (Rs Crs) :
 

61.68

Project Description :
 

Design, Supply & Laying of pipelines for bringing 11.10 mld treated water (16 hours flow) from the Source Pagara Dam, located near Village -Pagara , Block:- Jora , District – Morena , to 32 villages & 2 Urban towns

Silao

Project :
 

Silao Multi Village Piped Water Supply Scheme, Distt. Nalanda, Bihar

Client :
 

PHED, Patna

Project Value (Rs Crs) :
 

58.76

Project Description :
 

Design and build of all system components of Silao Multi village piped water supply Scheme including 5 years O&M on DBOT mode

Manpur

Project :
 

Manpur Multi village Water Supply Scheme, Distt. Umaria, M.P.

Client :
 

MPJNM, Bhopal

Project Value (Rs Crs) :
 

51.77

Project Description :
 

Design, Supply & Laying of pipelines for bringing 4.90 million litre of treated water (16 hours flow) from the Source Son River,located near Village - Baigawan, Block Manpur, District – Umaria, to 19 villages

Jamalpur

Project :
 

Augmentation of Complete Water Supply Scheme for Jamalpur Town

Client :
 

PHED, Bihar

Project Value (Rs Crs) :
 

31.57

Project Description :
 

Design, construction, testing and commissioning augmentation of drinking Water Supply Scheme including creation of water resource by constructing Intake Facility as Floating Jetty in the river Ganga and transmission of MS Pipe as well as Construction of Water Treatment Facility.

Munger

Project :
 

Augmentation of Complete Water Supply Scheme for Munger Town, Bihar

Client :
 

PHED, Bihar

Project Value (Rs Crs) :
 

27.77

Project Description :
 

Design, construction, testing and commissioning of augmentation of Water Supply Scheme including creation of water source by constructing Intake Facility as Floating Jetty in the river Ganga, Water Treatment Plant, Supplying and Laying of Rising Main of DI pipes and installation of distribution network.

DJB, Kalyanpuri

Project :
 

Sewage Pumping Station at Kalyanpuri STP

Client :
 

DJB, New Delhi

Project Value (Rs Crs) :
 

27.10

Project Description :
 

Design, Construction, Supply, Installation, Testing, Commissioning, Trial run, Operation and Maintenance during DLP and thereafter for 10 years, of 70 MGD Sewage Pumping Station, rising main and other related associated/allied appurtenant works.